Friable asbestos removal requires specialists who are qualified to undertake:
- set up of negative air units
- set up 3 stage decontamination units
- smoke test prior to start confirming encapsulation effective
- wire brush all timber’s
- vacuum entire ceiling space including back of tiles & sarking where exposed
- wet wipe hard stand services including cables
- visual inspection from asbestos assessor on completion
- paint entire ceiling space with airless paint gun
- Clearance monitoring inside ceiling space
- once clearance results received Remove encapsulation & double check all areas